Carina BESS
154.11 MW storage in Nueces, TX · In queue since June 2020 · Proposed COD April 2025
154.11 MW
Capacity
1
Components
Battery
5y 11m
In Queue
IA Executed
IA Status
Signed Aug 2021
Queue → IA
1y 2m
IA → COD
3y 8m
Total Duration
1y 2m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-04-14
The Carina BESS project is a proposed 154.11 MW battery storage project located in Nueces County, Texas. Developed by BRP Carina BESS LLC, the project entered the ERCOT interconnection queue as queue ID ERCOT-22INR0353 on June 26, 2020. The project's proposed commercial operation date is April 14, 2025, and its Interconnection Agreement (IA) was executed on August 3, 2021. The point of interconnection is listed as 88479 (138 kV CRINAPOI4A).
This development is linked to the existing Carina operating plant (EIA plant ID 65589). The Carina BESS project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Carina BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
88479 (138 kV CRINAPOI4A)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CARN_ESS_RN
- POI Substation
- Clarkwood Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26