XE Murat [Adlong] Solar
60.36 MW generation in Harris, TX · In queue since August 2020 · Proposed COD January 2025
60.36 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Status
Signed Mar 2022
Queue → IA
1y 7m
IA → COD
2y 10m
Total Duration
1y 7m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-01-31
The XE Murat [Adlong] Solar project is a proposed 60.36 MW solar generation project located in Harris County, Texas. The project, developed by Liberty 1 Solar, is interconnected within the ERCOT region under queue ID ERCOT-22INR0354. It entered the interconnection queue on August 4, 2020, and has a proposed commercial operation date of January 31, 2025.
The project's Interconnection Agreement (IA) was executed on March 4, 2022. The point of interconnection (POI) is at tap 138kV 40391 Crosby C66 - 40130 Atascocita. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Liberty 1 Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 40391 Crosby C66 - 40130 Atascocita
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about XE Murat [Adlong] Solar