Jungmann Solar
40.21 MW generation in Milam, TX · In queue since June 2020 · Proposed COD April 2025
40.21 MW
Capacity
1
Components
Solar
5y 11m
In Queue
IA Executed
IA Status
Signed Feb 2022
Queue → IA
1y 8m
IA → COD
3y 2m
Total Duration
1y 8m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-04-25
Jungmann Solar is a proposed solar generation project located in Milam County, Texas. The project, developed by BT Jungmann LLC, has a total capacity of 40.21 MW. It is listed in the ERCOT interconnection queue as entry ERCOT-22INR0356, with a queue entry date of June 3, 2020, and a proposed commercial operation date of April 25, 2025. The project's Interconnection Agreement (IA) was executed on February 15, 2022.
The proposed project is linked to the existing BT Jungmann operating plant (EIA ID 68246). The point of interconnection (POI) is Tap 69kV 3643 Temp SS - 3689 Marak c1. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Jungmann LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69kV 3643 Temp SS - 3689 Marak c1
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- POI Substation
- Marak Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.