Hayhurst Texas Solar (ERCOT-22INR0363) — Project Summary

Queue ID
ERCOT-22INR0363
Capacity
24.76 MW
Technology
Solar
Status
active
Location
Culberson, TX
Region
ERCOT
Developer
Hayhurst Texas Solar, LLC
IA Status
IA Executed

Hayhurst Texas Solar

ERCOT-22INR0363BetaActiveSolarERCOTLBNL + Live

24.76 MW generation in Culberson, TX · In queue since August 2020 · Proposed COD November 2025

24.76 MW

Capacity

1

Components

Solar

5y 9m

In Queue

IA Executed

IA Status

Signed Sep 2021

Interconnection

Queue → IA

1y 1m

IA → COD

4y 2m

Total Duration

1y 1m

Schedule

5 months past proposed COD

Construction75%
Queue EntryAug 21, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementSep 9, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-11-28

About

Hayhurst Texas Solar is a proposed solar generation project located in Culberson County, Texas. The project, with a total capacity of 24.76 MW, is being developed by Hayhurst Texas Solar, LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0363, with an interconnection queue entry date of August 21, 2020. The proposed commercial operation date is November 28, 2025, and the Interconnection Agreement (IA) was executed on September 9, 2021.

The project is linked to the existing operating Hayhurst Texas Solar facility (EIA plant ID 66880). The point of interconnection is the tap 138 kV Three Mile Draw Switch _x0013_ Horseshoe Springs Switch Line. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Culberson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Hayhurst Texas Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 138 kV Three Mile Draw Switch _x0013_ Horseshoe Springs Switch Line

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
HIGH
Nearest Node (Estimated)
CHAL_SLR_RN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Hayhurst Texas Solar