BRP Mensa BESS
404.99 MW storage in Pecos, TX · In queue since June 2020 · Proposed COD December 2027
404.99 MW
Capacity
1
Components
Battery
5y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The BRP Mensa BESS project is a proposed 404.99 MW battery storage project located in Pecos County, Texas. The developer is BRP Mensa BESS LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-22INR0365, with a queue entry date of June 26, 2020.
The project's proposed commercial operation date is December 1, 2027. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 60718 Pecos Valley 138kV.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Mensa BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60718 Pecos Valley 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Pecos Valley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.