Inertia Solar
202.39 MW generation in Haskell, TX · Proposed COD March 2029
202.39 MW
Capacity
1
Components
Solar
—
In Queue
IA Executed
IA Status
Signed May 2021
IA → COD
7y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-03-31
The Inertia Solar project is a proposed 202.39 MW solar generation project located in Haskell County, Texas. The developer is Inertia Solar Project, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0374. An Interconnection Agreement (IA) was executed on May 4, 2021. The proposed commercial operation date is March 31, 2029.
The point of interconnection (POI) is at tap 345kV 60515 Clear Crossing - 6104 Smoky Hill. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Inertia Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 60515 Clear Crossing - 6104 Smoky Hill
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- AZURE_RN
- POI Substation
- Clear Crossing Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.