BRP Musca BESS
100.51 MW storage in Reagan, TX · In queue since July 2020 · Proposed COD December 2027
100.51 MW
Capacity
1
Components
Battery
5y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
7y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The BRP Musca BESS project is a proposed 100.51 MW battery storage project located in Reagan County, Texas. The developer is BRP Musca BESS LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0383, with an interconnection queue entry date of July 24, 2020. The project's proposed commercial operation date is December 1, 2027, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 100.51 MW of battery storage capacity. The BRP Musca BESS project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Reagan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Musca BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60361 Santa Rita 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Santa Rita Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about BRP Musca BESS