BRP Pictor BESS (ERCOT-22INR0385) — Project Summary

Queue ID
ERCOT-22INR0385
Capacity
201.07 MW
Technology
Battery
Status
active
Location
Crane, TX
Region
ERCOT
Developer
BRP Pictor BESS LLC
IA Status
Facility Study

BRP Pictor BESS

ERCOT-22INR0385BetaActiveBatteryERCOTLBNL + Live

201.07 MW storage in Crane, TX · In queue since July 2020 · Proposed COD November 2025

201.07 MW

Capacity

1

Components

Battery

5y 10m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection

Total Duration

5y 4m

Schedule

6 months past proposed COD

Facilities Study50%
Queue EntryJul 24, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-01

About

The BRP Pictor BESS project is a proposed 201.07 MW battery storage project located in Crane County, Texas. Developed by BRP Pictor BESS LLC, the project consists of 201.07 MW of battery capacity.

The project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0385, with a queue entry date of July 24, 2020. Its proposed commercial operation date is November 1, 2025, and its interconnection agreement status is currently in the Facility Study phase.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Crane

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Pictor BESS LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

60400 Lynx 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
Nearest Node (Estimated)
HORSCR_RN
POI Substation
Lynx Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.