BRP Octans BESS
129.57 MW storage in Pecos, TX · In queue since July 2020 · Proposed COD December 2029
129.57 MW
Capacity
1
Components
Battery
5y 10m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The BRP Octans BESS project is a proposed 129.57 MW battery storage project located in Pecos County, Texas. The developer is BRP OCTANS BESS LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0386, with an interconnection queue entry date of July 24, 2020. The proposed commercial operation date is December 1, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The project is linked to the existing Octans operating plant (EIA ID 65590). The point of interconnection is the 6671 Tombstone 138kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP OCTANS BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6671 Tombstone 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- POI Substation
- Tombstone Substation