Cachi BESS
205.46 MW storage in Guadalupe, TX · In queue since August 2020 · Proposed COD March 2025
205.46 MW
Capacity
1
Components
Battery
5y 9m
In Queue
IA Executed
IA Status
Signed Jun 2021
Queue → IA
10 months
IA → COD
3y 9m
Total Duration
10 months
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-03-31
The Cachi BESS project is a proposed 205.46 MW battery storage project located in Guadalupe County, Texas. The developer is BRP Cachi BESS LLC. This project is interconnected within the ERCOT region under queue ID ERCOT-22INR0388, with an interconnection queue entry date of August 21, 2020. The proposed commercial operation date is March 31, 2025, and the Interconnection Agreement (IA) was executed on June 11, 2021.
The project is linked to the existing Cachi operating plant (EIA ID 65861). The Cachi BESS development project has also been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Guadalupe
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Cachi BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7680 Clear Springs 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CACH_ESS_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26