Dragan Storage
408.3 MW storage in Comanche, TX · In queue since August 2020 · Proposed COD February 2026
408.3 MW
Capacity
1
Components
Battery
5y 9m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-28
The Dragan Storage project is a proposed 408.3 MW battery storage project located in Comanche County, Texas. The developer is Hecate Grid Dragan Storage LLC. It is interconnected to the ERCOT grid under queue ID ERCOT-22INR0400, with an interconnection queue entry date of August 21, 2020. The proposed commercial operation date is February 28, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The Dragan Storage project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hecate Grid Dragan Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1440 Comanche 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CPSES_UNIT1
- POI Substation
- Comanche Peak Station