BRP Pular BESS
233.1 MW storage in Hidalgo, TX · In queue since September 2020 · Proposed COD December 2027
233.1 MW
Capacity
1
Components
Battery
5y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The BRP Pular BESS project is a proposed 233.1 MW battery storage project located in Hidalgo County, Texas. The developer is BRP Pular BESS LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-22INR0408, with a queue entry date of September 11, 2020, and a proposed commercial operation date of December 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The BRP Pular BESS project has been the subject of recent news coverage, with two articles focusing on deals related to the project.
Generated from interconnection queue and public data sources
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Pular BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8963 Hidalgo Energy Center 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26