LUBIO SOLAR
54.47 MW generation in Kaufman, TX · In queue since October 2020 · Proposed COD April 2028
54.47 MW
Capacity
1
Components
Solar
5y 7m
In Queue
IA Executed
IA Status
Signed Nov 2024
Queue → IA
4y 1m
IA → COD
3y 5m
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-20
The Lubio Solar project is a proposed 54.47 MW solar generation project located in Kaufman County, Texas. The project, developed by BDPU Solar Lubio LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0426, with a queue entry date of October 7, 2020. The proposed commercial operation date is April 20, 2028.
The project has an Interconnection Agreement (IA) executed on November 8, 2024. The point of interconnection (POI) is at the tap 138kV 2727 Crandall - 2724 Kaufman Northwest.
Generated from interconnection queue and public data sources
State
TX
County
Kaufman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BDPU Solar Lubio LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 2727 Crandall - 2724 Kaufman Northwest
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about LUBIO SOLAR