TORMES SOLAR
382.12 MW generation in Navarro, TX · In queue since October 2020 · Proposed COD March 2027
382.12 MW
Capacity
1
Components
Solar
5y 7m
In Queue
IA Executed
IA Status
Signed Apr 2024
Queue → IA
3y 6m
IA → COD
2y 11m
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-31
The TORMES SOLAR project is a proposed 382.12 MW solar generation facility in Navarro County, Texas. The project, developed by BDPU Solar Tormes LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0437, with a queue entry date of October 23, 2020. The proposed commercial operation date is March 31, 2027.
The project's Interconnection Agreement (IA) has been executed as of April 10, 2024. The point of interconnection is at the tap 345kV 1906 Venus - 68091 Navarro. The TORMES SOLAR project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BDPU Solar Tormes LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1906 Venus - 68091 Navarro
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DSWL_BES1
- POI Substation
- Venus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.