Liberty Senate Solar 1
202 MW generation in Jack, TX · In queue since March 2021 · Proposed COD October 2025
202 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
4y 7m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-27
Liberty Senate Solar 1 is a proposed 202 MW solar generation project located in Jack County, Texas. The developer is Senate Solar LLC. The project is in the ERCOT interconnection queue as entry ERCOT-22INR0444, with a queue entry date of March 1, 2021, and a proposed commercial operation date of October 27, 2025. Its interconnection status is currently in the Facility Study phase.
The development project consists of 202 MW of solar photovoltaic generation. Liberty Senate Solar 1 has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
TX
County
Jack
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Senate Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1445 Burwick 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Liberty Senate Solar 1