SPC Bloom BESS
100 MW storage in Victoria, TX · In queue since December 2020 · Proposed COD April 2027
100 MW
Capacity
1
Components
Battery
5y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-07
The SPC Bloom BESS project is a proposed 100 MW battery storage project located in Victoria County, Texas. The developer is BRP Blue Topaz 2, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0445, with a queue entry date of December 3, 2020. The proposed commercial operation date is April 7, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 100 MW of battery storage capacity. It is interconnected to the grid at the 8911 Black Bayou 138kV point of interconnection. The SPC Bloom BESS project has appeared in recent news coverage regarding energy storage developments in the ERCOT region.
Generated from interconnection queue and public data sources
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Blue Topaz 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8911 Black Bayou 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Black Bayou Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.