Anson BAT
150.6 MW storage in Jones, TX · In queue since December 2020 · Proposed COD December 2027
150.6 MW
Capacity
1
Components
Battery
5y 5m
In Queue
IA Executed
IA Status
Signed Aug 2024
Queue → IA
3y 8m
IA → COD
3y 4m
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-12-01
The Anson BAT project is a proposed 150.6 MW battery storage project located in Jones County, Texas. The developer is Anson II Storage LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0457, with an interconnection queue entry date of December 3, 2020. The proposed commercial operation date is December 1, 2027.
The project's Interconnection Agreement (IA) has been executed as of August 15, 2024. The point of interconnection is at the tap 345 kV 68004 Phantom Hill station. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anson II Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68004 Phantom Hill station
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.