70.44 MW storage in Travis, TX · In queue since February 2021 · Proposed COD December 2026
70.44 MW
Capacity
1
Components
Battery
5y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The Venture Hill Storage project is a proposed 70.44 MW battery storage project located in Travis County, Texas. Developed by KCE TX 24, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0488, with a queue entry date of February 9, 2021. The proposed commercial operation date is December 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The Venture Hill Storage project has been the subject of recent news coverage, with seven articles published related to the project. These articles primarily focus on deals, regulatory matters, and industry news.
Generated from interconnection queue and public data sources
State
TX
County
Travis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
KCE TX 24, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7336 Gilleland Creek 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SLCN_ESS_ALL
- POI Substation
- Gilleland Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26