TEXPO
680 MW generation in Wilbarger, TX · In queue since March 2021 · Proposed COD October 2027
680 MW
Capacity
1
Components
Gas
5y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
The TEXPO project is a proposed 680 MW natural gas generation project in Wilbarger County, Texas. Developed by Oklaunion Power Station, LLC, the project entered the ERCOT interconnection queue as ERCOT-22INR0497 on March 16, 2021. Its proposed commercial operation date is October 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project is to be located at the Point of Interconnection (POI) 6100 Oklaunion 345kV. The TEXPO project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Oklaunion Power Station, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6100 Oklaunion 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DC_N
- POI Substation
- Oklaunion North Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.