Roseland Solar II (ERCOT-22INR0506) — Project Summary

Queue ID
ERCOT-22INR0506
Capacity
254 MW
Technology
Solar
Status
active
Location
Falls, TX
Region
ERCOT
Developer
Enel Green Power Roseland Solar, LLC
IA Status
IA Executed

Roseland Solar II

ERCOT-22INR0506BetaActiveSolarERCOTLBNL + Live

254 MW generation in Falls, TX · In queue since October 2021 · Proposed COD November 2025

254 MW

Capacity

1

Components

Solar

4y 7m

In Queue

IA Executed

IA Status

Signed Dec 2020

Interconnection

IA → COD

4y 11m

Total Duration

4y 7m

Schedule

5 months past proposed COD

Construction75%
Queue EntryOct 5, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 10, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-11-29

About

Roseland Solar II is a proposed 254 MW solar generation project located in Falls County, Texas. The developer is Enel Green Power Roseland Solar, LLC. The project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-22INR0506 on October 5, 2021. The proposed commercial operation date is November 29, 2025, and the Interconnection Agreement has been executed as of December 10, 2020.

The point of interconnection is at tap 345kV 3390 Jewett - 3399 Ratsnake. The project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Falls

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Enel Green Power Roseland Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 3390 Jewett - 3399 Ratsnake

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Jewett Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.