Roseland Solar II
254 MW generation in Falls, TX · In queue since October 2021 · Proposed COD November 2025
254 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Status
Signed Dec 2020
IA → COD
4y 11m
Total Duration
4y 7m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-11-29
Roseland Solar II is a proposed 254 MW solar generation project located in Falls County, Texas. The developer is Enel Green Power Roseland Solar, LLC. The project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-22INR0506 on October 5, 2021. The proposed commercial operation date is November 29, 2025, and the Interconnection Agreement has been executed as of December 10, 2020.
The point of interconnection is at tap 345kV 3390 Jewett - 3399 Ratsnake. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Falls
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Enel Green Power Roseland Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 3390 Jewett - 3399 Ratsnake
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Jewett Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.