Pine Forest BESS (ERCOT-22INR0526) — Project Summary

Queue ID
ERCOT-22INR0526
Capacity
200.74 MW
Technology
Battery
Status
active
Location
Hopkins, TX
Region
ERCOT
Developer
Pine Forest Hybrid I, LLC
IA Status
IA Executed

Pine Forest BESS

ERCOT-22INR0526BetaActiveBatteryERCOTLBNL + Live

200.74 MW storage in Hopkins, TX · In queue since May 2021 · Proposed COD February 2026

200.74 MW

Capacity

1

Components

Battery

5 years

In Queue

IA Executed

IA Status

Signed Apr 2024

Interconnection

Queue → IA

2y 11m

IA → COD

1y 10m

Total Duration

2y 11m

Schedule

2 months past proposed COD

Construction75%
Queue EntryMay 4, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 10, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-02-27

About

Pine Forest BESS is a proposed 200.74 MW battery storage project in Hopkins County, Texas. The project, developed by Pine Forest Hybrid I, LLC, is located within the ERCOT region and consists entirely of battery storage.

The project entered the ERCOT interconnection queue as entry 22INR0526 on May 4, 2021, with a proposed commercial operation date of February 27, 2026. The interconnection agreement for the project was executed on April 10, 2024. The point of interconnection is at the tap 345kV 1696 Monticello SES - 2514 Allen Switch.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hopkins

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Pine Forest Hybrid I, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 1696 Monticello SES - 2514 Allen Switch

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Monticello substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.