Midlothian Unit 3 repower
18 MW generation in Ellis, TX · In queue since May 2021 · Proposed COD December 2026
18 MW
Capacity
1
Components
Gas
5 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-03
The Midlothian Unit 3 repower is a proposed 18 MW gas-fired generation project located in Ellis County, Texas. The project, developed by Midlothian Energy, LLC, is listed in the ERCOT interconnection queue as entry ERCOT-22INR0543, with a queue entry date of May 24, 2021. The proposed commercial operation date is December 3, 2026.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 1940 Midlothian ELP 345kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
MIDLOTHIAN ENERGY, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1940 Midlothian ELP 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Midlothian South Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.