TE Smith Storage
125.36 MW storage in Rockwall, TX · In queue since September 2021 · Proposed COD January 2026
125.36 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
2y 2m
IA → COD
2y 2m
Total Duration
2y 2m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-01-15
The TE Smith Storage project is a proposed 125.36 MW battery storage project located in Rockwall County, Texas. The developer is BT Smith Storage, LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0555, with an interconnection queue entry date of September 2, 2021, and a proposed commercial operation date of January 15, 2026. The project's Interconnection Agreement (IA) was executed on November 8, 2023.
The TE Smith Storage project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Rockwall
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Smith Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
2483 Royse Switch 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about TE Smith Storage