Muenster BESS (ERCOT-22INR0590) — Project Summary

Queue ID
ERCOT-22INR0590
Capacity
9.9 MW
Technology
Battery
Status
active
Location
Cooke, TX
Region
ERCOT
Developer
Regis Development I, LLC
IA Status
IA Executed

Muenster BESS

ERCOT-22INR0590BetaActiveBatteryERCOTLBNL

9.9 MW storage in Cooke, TX · Proposed COD March 2025

9.9 MW

Capacity

1

Components

Battery

In Queue

IA Executed

IA Status

Signed Jul 2023

Interconnection

IA → COD

1y 8m

Schedule

14 months past proposed COD

Construction75%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 12, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-03-04

About

The Muenster BESS project is a proposed 9.9 MW battery storage project located in Cooke County, Texas. Developed by Regis Development I, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-22INR0590. The proposed commercial operation date is March 4, 2025.

The project's interconnection agreement was executed on July 12, 2023. The point of interconnection is the Muenster substation at 138kV. The project is currently listed as active in the ERCOT interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Cooke

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Regis Development I, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Station Name (TDSP Station Code): Muenster Load/Load Transformer Name: Muenster1 PTI BUS number: 695 Voltage in kV (Transmission Level): 138kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Muenster BESS