Camino Santiago Solar
196.3 MW generation in Milam, TX · In queue since September 2022 · Proposed COD February 2027
196.3 MW
Capacity
1
Components
Solar
3y 8m
In Queue
IA Executed
IA Status
Signed Dec 2024
Queue → IA
2y 3m
IA → COD
2y 2m
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-02-18
The Camino Santiago Solar project is a proposed 196.3 MW solar generation project located in Milam County, Texas. The developer is Camino Solar Project, LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0605, with a queue entry date of September 2, 2022, and a proposed commercial operation date of February 18, 2027.
The project's Interconnection Agreement (IA) has been executed as of December 6, 2024. The point of interconnection (POI) is at Tap 345kV 3687 Bell County East Switch _x0013_ 39950 TNP One Plant Ckt 2 (North Circuit). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Camino Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3687 Bell County East Switch _x0013_ 39950 TNP One Plant Ckt 2 (North Circuit).
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Camino Santiago Solar