Cedar Bayou 5 (TEF - Due Diligence) (ERCOT-23INR0029) — Project Summary

Queue ID
ERCOT-23INR0029
Capacity
697 MW
Technology
Gas
Status
active
Location
Chambers, TX
Region
ERCOT
Developer
NRG Cedar Bayou 5 LLC
IA Status
IA Executed

Cedar Bayou 5 (TEF - Due Diligence)

ERCOT-23INR0029BetaActiveGasERCOTLBNL + Live

697 MW generation in Chambers, TX · In queue since March 2020 · Proposed COD December 2027

697 MW

Capacity

1

Components

Gas

6y 2m

In Queue

IA Executed

IA Status

Signed Jan 2022

Interconnection

Queue → IA

1y 10m

IA → COD

5y 11m

Total Duration

1y 10m

Construction75%
Queue EntryMar 26, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 10, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2027-12-15

About

The Cedar Bayou 5 (TEF - Due Diligence) project is a proposed 697 MW gas-fired generation project located in Chambers County, Texas. Developed by NRG Cedar Bayou 5 LLC, the project entered the ERCOT interconnection queue as queue ID ERCOT-23INR0029 on March 26, 2020, with a proposed commercial operation date of December 15, 2027. The project has an executed Interconnection Agreement (IA) dated January 10, 2022.

This development is linked to the existing Cedar Bayou 5 operating plant (EIA plant ID 68606). The project has been the subject of recent news coverage, with 10 articles related to deals and industry developments.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Chambers

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NRG Cedar Bayou 5 LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

40000 Cedar Bayou 345kV

Data Source

LBNL + Live

DeveloperNRG EnergyUtility Dive · 2025-09-29
TransactionDebt financingUtility Dive · 2025-09-29
Deal value$562.0MUtility Dive · 2025-09-29
LenderPublic Utility Commission of TexasUtility Dive · 2025-09-29
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
HIGH
Nearest Node (Estimated)
CBY5_CC1

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles