Dori BQ Solar
50.42 MW generation in Harris, TX · In queue since June 2020 · Proposed COD August 2027
50.42 MW
Capacity
1
Components
Solar
5y 11m
In Queue
IA Executed
IA Status
Signed Dec 2022
Queue → IA
2y 6m
IA → COD
4y 8m
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-08-30
The Dori BQ Solar project is a proposed 50.42 MW solar generation project located in Harris County, Texas. The project, developed by Sunnyside Energy, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0040, with a queue entry date of June 9, 2020. The proposed commercial operation date is August 30, 2027.
The project has an executed Interconnection Agreement (IA), dated December 1, 2022. The point of interconnection (POI) is tap 138kV 47210 Holmes _x0013_ 42680 Garden Villas.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sunnyside Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 47210 Holmes _x0013_ 42680 Garden Villas
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.