Equinox Storage (ERCOT-23INR0048) — Project Summary

Queue ID
ERCOT-23INR0048
Capacity
101.2 MW
Technology
Battery
Status
active
Location
Starr, TX
Region
ERCOT
Developer
Invenergy Storage Development LLC
IA Status
Facility Study

Equinox Storage

ERCOT-23INR0048BetaActiveBatteryERCOTLBNL

101.2 MW storage in Starr, TX · In queue since June 2020 · Proposed COD December 2026

101.2 MW

Capacity

1

Components

Battery

5y 11m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

6y 6m

Facilities Study50%
Queue EntryJun 26, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-30

About

The proposed Equinox Storage project is a 101.2 MW battery energy storage system located in Starr County, Texas. Developed by Invenergy Storage Development LLC, the project is currently in the ERCOT interconnection queue as entry ERCOT-23INR0048, with a queue entry date of June 26, 2020. The project's proposed commercial operation date is December 30, 2026, and its interconnection agreement status is currently in the Facility Study phase.

The Equinox Storage project has been mentioned in recent news coverage related to the energy industry.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Starr

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Invenergy Storage Development LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

80355 Del Sol 345kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Mesa del Sol Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.