Noria Solar DCC
145 MW generation in Nueces, TX · In queue since August 2020 · Proposed COD October 2027
145 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Status
Signed Oct 2022
Queue → IA
2y 2m
IA → COD
5 years
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-10-01
The Noria Solar DCC project is a proposed 145 MW solar generation project located in Nueces County, Texas. Developed by Noria Hondo Solar, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0061. The project entered the interconnection queue on August 4, 2020, and has a proposed commercial operation date of October 1, 2027.
The project's Interconnection Agreement (IA) was executed on October 12, 2022. The point of interconnection (POI) is the 85000 Nelson Sharpe 345kV location. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Noria Hondo Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
85000 Nelson Sharpe 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SHAFFER_ALL
- POI Substation
- Nelson Sharpe Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.