Noria Storage (ERCOT-23INR0062) — Project Summary

Queue ID
ERCOT-23INR0062
Capacity
75 MW
Technology
Battery
Status
active
Location
Nueces, TX
Region
ERCOT
Developer
Noria Hondo Solar, LLC
IA Status
IA Executed

Noria Storage

ERCOT-23INR0062BetaActiveBatteryERCOTLBNL

75 MW storage in Nueces, TX · In queue since August 2020 · Proposed COD October 2026

75 MW

Capacity

1

Components

Battery

5y 9m

In Queue

IA Executed

IA Status

Signed Oct 2022

Interconnection

Queue → IA

2y 2m

IA → COD

4 years

Total Duration

2y 2m

Construction75%
Queue EntryAug 4, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 12, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-10-13

About

The Noria Storage project is a proposed 75 MW battery energy storage system in Nueces County, Texas. Developed by Noria Hondo Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0062, with a queue entry date of August 4, 2020. The proposed commercial operation date is October 13, 2026.

The project's Interconnection Agreement (IA) has been executed as of October 12, 2022. The point of interconnection (POI) is the 85000 Nelson Sharpe 345kV location.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Nueces

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Noria Hondo Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

85000 Nelson Sharpe 345kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SHAFFER_ALL
POI Substation
Nelson Sharpe Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Noria Storage