Accalia Point Solar
190.5 MW generation in Cameron, TX · In queue since October 2020 · Proposed COD May 2029
190.5 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
8y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-31
Accalia Point Solar is a proposed 190.5 MW solar generation project located in Cameron County, Texas. The project, developed by Accalia Point Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0066, with a queue entry date of October 23, 2020. Its proposed commercial operation date is May 31, 2029, and its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Accalia Point Solar, LLC operating plant (EIA ID 66673). The point of interconnection is Tap 345kV 8383 North Edingburg _x0013_ 79501 Kingfisher.
Generated from interconnection queue and public data sources
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Accalia Point Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 8383 North Edingburg _x0013_ 79501 Kingfisher
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MESQUITE_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Accalia Point Solar