Cannon Solar SLF
80 MW generation in Gonzales, TX · In queue since September 2020 · Proposed COD December 2027
80 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The Cannon Solar SLF project is a proposed 80 MW solar generation facility in Gonzales County, Texas. Developed by Cannon Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0076, with a queue entry date of September 11, 2020. The proposed commercial operation date is December 31, 2027, and the project's interconnection status is currently in the Facility Study phase.
The point of interconnection is the tap 138kV 7224 Luling - 7245 Gonzales. The Cannon Solar SLF project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
TX
County
Gonzales
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cannon Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 7224 Luling - 7245 Gonzales
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Luling Magnolia Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.