Shaw Solar
124.65 MW generation in Bandera, TX · In queue since October 2020 · Proposed COD April 2026
124.65 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 6m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-29
Shaw Solar is a proposed solar generation project located in Bandera County, Texas, with a total capacity of 124.65 MW. The project, developed by Rio Lago Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0078, with a queue entry date of October 23, 2020. The proposed commercial operation date is April 29, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The Shaw Solar project has been the subject of recent news coverage, with five articles related to the industry, deals, and development of the project.
Generated from interconnection queue and public data sources
State
TX
County
Bandera
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rio Lago Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 7146 Verde Creek - 7438 Bandera
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Verde Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Shaw Solar