Alila Solar
256.5 MW generation in San Patricio, TX · In queue since October 2020 · Proposed COD April 2028
256.5 MW
Capacity
1
Components
Solar
5y 7m
In Queue
IA Executed
IA Status
Signed Jan 2023
Queue → IA
2y 3m
IA → COD
5y 3m
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-20
The Alila Solar project is a proposed 256.5 MW solar generation facility in San Patricio County, Texas. Developed by Electra Energy Project, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0093, with a queue entry date of October 7, 2020. The proposed commercial operation date is April 20, 2028.
The project has an executed Interconnection Agreement (IA), dated January 3, 2023. The Point of Interconnection (POI) is the 8249 Angstrom 345kV substation. The Alila Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
San Patricio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Electra Energy Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8249 Angstrom 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Alila Solar