Burksol BESS
103.27 MW storage in Dickens, TX · In queue since October 2020 · Proposed COD March 2025
103.27 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Status
Signed Nov 2022
Queue → IA
2y 1m
IA → COD
2y 4m
Total Duration
2y 1m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-03-12
The Burksol BESS project is a proposed 103.27 MW battery storage project in Dickens County, Texas. The developer is Burksol LLC. It is interconnected within the ERCOT queue as entry ERCOT-23INR0103, with a queue entry date of October 23, 2020, and a proposed commercial operation date of March 12, 2025. The project's Interconnection Agreement (IA) was executed on November 17, 2022.
The project is linked to the existing Burksol Energy Storage operating plant (EIA ID 67968). The Burksol BESS project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dickens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Burksol LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59904 Cottonwood 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- W_CW_345BUS1
- POI Substation
- Cottonwood Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26