BRP Kamet BESS (ERCOT-23INR0104) — Project Summary

Queue ID
ERCOT-23INR0104
Capacity
202.46 MW
Technology
Battery
Status
active
Location
Andrews, TX
Region
ERCOT
Developer
BRP Kamet BESS LLC
IA Status
Facility Study

BRP Kamet BESS

ERCOT-23INR0104BetaActiveBatteryERCOTLBNL + Live

202.46 MW storage in Andrews, TX · In queue since October 2020 · Proposed COD December 2025

202.46 MW

Capacity

1

Components

Battery

5y 7m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection

Total Duration

5y 2m

Schedule

5 months past proposed COD

Facilities Study50%
Queue EntryOct 7, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

About

BRP Kamet BESS is a proposed 202.46 MW battery storage project located in Andrews County, Texas. The project, developed by BRP Kamet BESS LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0104, with a queue entry date of October 7, 2020. The proposed commercial operation date is December 1, 2025.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Andrews North _x0013_ McKenzie Draw Switch 138 kV. Recent news coverage has discussed the development project.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Andrews

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Kamet BESS LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Andrews North _x0013_ McKenzie Draw Switch 138 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about BRP Kamet BESS