Cantaloupe Storage (ERCOT-23INR0117) — Project Summary

Queue ID
ERCOT-23INR0117
Capacity
251.05 MW
Technology
Battery
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
Saragosa Del Sol Energy, LLC
IA Status
IA Executed

Cantaloupe Storage

ERCOT-23INR0117BetaActiveBatteryERCOTLBNL

251.05 MW storage in Reeves, TX · In queue since December 2020 · Proposed COD July 2028

251.05 MW

Capacity

1

Components

Battery

5y 5m

In Queue

IA Executed

IA Status

Signed Apr 2024

Interconnection

Queue → IA

3y 4m

IA → COD

4y 3m

Total Duration

3y 4m

Construction75%
Queue EntryDec 22, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 23, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-07-01

About

The Cantaloupe Storage project is a proposed 251.05 MW battery storage project in Reeves County, Texas. Developed by Saragosa Del Sol Energy, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0117. The project entered the interconnection queue on December 22, 2020, and has a proposed commercial operation date of July 1, 2028.

The interconnection agreement for the Cantaloupe Storage project was executed on April 23, 2024. The point of interconnection is the 60716 Saragosa 138kV location. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Reeves

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Saragosa Del Sol Energy, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

60716 Saragosa 138kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Saragosa Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Cantaloupe Storage