Blevins Solar
271.58 MW generation in Falls, TX · In queue since February 2021 · Proposed COD March 2026
271.58 MW
Capacity
1
Components
Solar
5y 3m
In Queue
IA Executed
IA Status
Signed Jun 2023
Queue → IA
2y 4m
IA → COD
2y 9m
Total Duration
2y 4m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-06
Blevins Solar is a proposed solar generation project located in Falls County, Texas, within the ERCOT region. The project, developed by Blevins Solar, LLC, has a total capacity of 271.58 MW. It consists entirely of solar photovoltaic generation.
The project entered the ERCOT interconnection queue as entry 23INR0118 on February 4, 2021, with a proposed commercial operation date of March 6, 2026. An Interconnection Agreement (IA) was executed on June 17, 2023. The project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Falls
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Blevins Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Bellfalls Switch (3404) _x0013_ Lake Creek Switch (3409)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Blevins Solar