Elbus BESS
200.99 MW storage in Caldwell, TX · In queue since December 2020 · Proposed COD June 2028
200.99 MW
Capacity
1
Components
Battery
5y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The Elbus BESS project is a proposed 200.99 MW battery storage project located in Caldwell County, Texas. Developed by BRP Elbus BESS LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0135, with a queue entry date of December 3, 2020.
The proposed commercial operation date for the Elbus BESS project is June 1, 2028. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the 9075 Lytton 138kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Caldwell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Elbus BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
9075 Lytton 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Lytton Springs Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.