BRP Passu BESS
301.82 MW storage in Wilbarger, TX · In queue since December 2020 · Proposed COD December 2028
301.82 MW
Capacity
1
Components
Battery
5y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The BRP Passu BESS project is a proposed 301.82 MW battery storage project located in Wilbarger County, Texas. Developed by BRP Passu BESS LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0139, with a queue entry date of December 3, 2020. The proposed commercial operation date is December 31, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the project is the 6111 Riley 345kV location. The project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Passu BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6111 Riley 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ELECTRAW_1_2
- POI Substation
- Riley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.