Umbra (Stockyard) Solar
207.84 MW generation in Franklin, TX · In queue since January 2021
207.84 MW
Capacity
1
Components
Solar
5y 4m
In Queue
—
IA Status
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Umbra (Stockyard) Solar project is a 207.84 MW solar generation facility located in Franklin County, Texas. The project is listed in the ERCOT interconnection queue as entry ERCOT-23INR0155, with an initial queue entry date of January 25, 2021.
As of the latest data, the project's interconnection status is listed as suspended. No proposed commercial operation date or interconnection agreement (IA) status is available. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
TX
County
Franklin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Umbra (Stockyard) Solar