Redonda Solar (ERCOT-23INR0162) — Project Summary

Queue ID
ERCOT-23INR0162
Capacity
253.21 MW
Technology
Solar
Status
active
Location
Zapata, TX
Region
ERCOT
Developer
J&R Power DevCo, LLC
IA Status
IA Executed

Redonda Solar

ERCOT-23INR0162BetaActiveSolarERCOTLBNL

253.21 MW generation in Zapata, TX · In queue since January 2021 · Proposed COD December 2026

253.21 MW

Capacity

1

Components

Solar

5y 4m

In Queue

IA Executed

IA Status

Signed Dec 2021

Interconnection

Queue → IA

11 months

IA → COD

5 years

Total Duration

11 months

Construction75%
Queue EntryJan 25, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 28, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-30

About

Redonda Solar is a proposed 253.21 MW solar generation project located in Zapata County, Texas. The project, developed by J&R Power DevCo, LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0162, with a queue entry date of January 25, 2021. The proposed commercial operation date is December 30, 2026.

The project's interconnection agreement (IA) was executed on December 28, 2021. The point of interconnection (POI) is at the tap 345kV 80307 Del Sol - 80225 Cenizo. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Zapata

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

J&R Power DevCo, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 80307 Del Sol - 80225 Cenizo

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Mesa del Sol Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Redonda Solar