Ringtail Ridge Storage
100.57 MW storage in Kendall, TX · In queue since January 2021 · Proposed COD May 2028
100.57 MW
Capacity
1
Components
Battery
5y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-23
Ringtail Ridge Storage is a proposed 100.57 MW battery storage project located in Kendall County, Texas. The developer is KCE TX 26, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-23INR0163, with an interconnection queue entry date of January 25, 2021. The proposed commercial operation date is May 23, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The Ringtail Ridge Storage project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Kendall
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
KCE TX 26, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7150 Kendall 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HHOLLW2_WND1
- POI Substation
- Horse Hollow Kendall Tie
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Ringtail Ridge Storage