Great Kiskadee Storage (ERCOT-23INR0166) — Project Summary

Queue ID
ERCOT-23INR0166
Capacity
103.05 MW
Technology
Battery
Status
active
Location
Hidalgo, TX
Region
ERCOT
Developer
Great Kiskadee Storage, LLC
IA Status
IA Executed

Great Kiskadee Storage

ERCOT-23INR0166BetaActiveBatteryERCOTLBNL

103.05 MW storage in Hidalgo, TX · In queue since January 2021 · Proposed COD January 2025

103.05 MW

Capacity

1

Components

Battery

5y 4m

In Queue

IA Executed

IA Status

Signed Jun 2022

Interconnection

Queue → IA

1y 5m

IA → COD

2y 7m

Total Duration

1y 5m

Schedule

16 months past proposed COD

Construction75%
Queue EntryJan 26, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 30, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-01-03

About

The Great Kiskadee Storage project is a proposed 103.05 MW battery storage project located in Hidalgo County, Texas. Developed by Great Kiskadee Storage, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0166. The project entered the queue on January 26, 2021, with a proposed commercial operation date of January 3, 2025. An Interconnection Agreement (IA) has been executed as of June 30, 2022.

The proposed project is linked to the existing Great Kiskadee Storage operating plant (EIA plant ID 68189). The project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hidalgo

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Great Kiskadee Storage, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

8951 Stewart Rd 138kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
GKS_BESS_RN
POI Substation
Stewart Road Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Great Kiskadee Storage