Goodalta Solar
221.36 MW generation in Navarro, TX · In queue since January 2021 · Proposed COD September 2027
221.36 MW
Capacity
1
Components
Solar
5y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-20
The Goodalta Solar project is a proposed 221.36 MW solar generation facility in Navarro County, Texas. Developed by GoodAlta Power Center LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0171, with a queue entry date of January 25, 2021. The proposed commercial operation date is September 20, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is tap 138kV 3127 Trinidad - 212 Winkler. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GoodAlta Power Center LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 3127 Trinidad - 212 Winkler
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- TRSES_UNIT6
- POI Substation
- Trinidad Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Goodalta Solar