Jackalope Solar
155.68 MW generation in San Patricio, TX · In queue since February 2021 · Proposed COD February 2026
155.68 MW
Capacity
1
Components
Solar
5y 3m
In Queue
IA Executed
IA Status
Signed Sep 2021
Queue → IA
7 months
IA → COD
4y 5m
Total Duration
7 months
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-02-05
Jackalope Solar is a proposed 155.68 MW solar generation project located in San Patricio County, Texas. The project, developed by Peacock Energy Project, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0180. It consists of 155.68 MW of solar photovoltaic generation.
The project entered the ERCOT interconnection queue on February 9, 2021, with a proposed commercial operation date of February 5, 2026. An Interconnection Agreement (IA) was executed on September 30, 2021, and the project's interconnection point of contact is the 8173 Gibbs 138kV substation. The project currently has an active status in the queue.
Generated from interconnection queue and public data sources
State
TX
County
San Patricio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Peacock Energy Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8173 Gibbs 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Jackalope Solar