Pradera Storage
153.11 MW storage in Webb, TX · In queue since January 2021 · Proposed COD March 2027
153.11 MW
Capacity
1
Components
Battery
5y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-31
The Pradera Storage project is a proposed 153.11 MW battery energy storage system in Webb County, Texas. Developed by Pradera Storage, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0183, with a queue entry date of January 25, 2021. The proposed commercial operation date is March 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 345 kV Lobo 80219 - Fowlerton 5709 ckt #2. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pradera Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV Lobo 80219 - Fowlerton 5709 ckt #2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pradera Storage