Bayside Solar
508.9 MW generation in Victoria, TX · In queue since February 2021
508.9 MW
Capacity
1
Components
Solar
5y 3m
In Queue
—
IA Status
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Bayside Solar is a proposed 508.9 MW solar generation project located in Victoria County, Texas. The development project is in the ERCOT interconnection queue as entry ERCOT-23INR0189, with a queue entry date of February 9, 2021. The project's status is currently listed as suspended.
The proposed project, under the name Bayside Solar, has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.