Pequin Energy Storage (ERCOT-23INR0194) — Project Summary

Queue ID
ERCOT-23INR0194
Capacity
103.4 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Pequin Energy Storage, LLC
IA Status
Facility Study

Pequin Energy Storage

ERCOT-23INR0194BetaActiveBatteryERCOTLBNL + Live

103.4 MW storage in Brazoria, TX · In queue since January 2021 · Proposed COD September 2027

103.4 MW

Capacity

1

Components

Battery

5y 4m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

6y 8m

Facilities Study50%
Queue EntryJan 25, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-13

About

Pequin Energy Storage is a proposed 103.4 MW battery storage project located in Brazoria County, Texas. The project, developed by Pequin Energy Storage, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0194, with a queue entry date of January 25, 2021. Its proposed commercial operation date is September 13, 2027, and its interconnection agreement status is currently in the Facility Study phase.

The project consists of a 103.4 MW battery energy storage system. The point of interconnection is the 39500 TN West Columbia 138kV. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Pequin Energy Storage, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

39500 TN West Columbia 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
MEDIUM
Nearest Node (Estimated)
NCO_RN
POI Substation
West Columbia Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.