SUNSETTER BESS
100 MW storage in Uvalde, TX · In queue since February 2021 · Proposed COD November 2027
100 MW
Capacity
1
Components
Battery
5y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-30
The SUNSETTER BESS project is a proposed 100 MW battery storage project located in Uvalde County, Texas. Developed by CED Development Inc., the project consists of a 100 MW battery energy storage system (BESS).
The project is currently in the ERCOT interconnection queue as entry ERCOT-23INR0205, with a queue entry date of February 9, 2021. Its proposed commercial operation date is November 30, 2027, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 5885 Downie 138kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Uvalde
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5885 Downie 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HELIOS_RN
- POI Substation
- Downie Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.